Parc Fotovoltaic Solarist Tismana 2 - Parc Verde

Main activities of the TISMANA 2 SOLARIST PHOTOVOLTAIC PARK

The design and execution of a photovoltaic park with an installed power of 132 MW on the slag and ash deposits of the spoil tip in Tismana 2 Quarry – E.M.C. Roșia-Rovinari.

Project developed by
Supported by

TISMANA 2 SOLARIST
PHOTOVOLTAIC PARK AT A GLANCE

Project name

Construction of a Photovoltaic Park on the inner dump Tismana 2 - Roșia - Rovinari quarry mining unit

The total value of the project is 572,613,097 lei (equivalent in lei of 115,357,810 euro), of which the maximum insured value from the Modernization Fund is 400,829,168 lei (equivalent in lei of 80,750,467 euro -70% of the total value of the Project).

Location

The Tismana 2 solar photovoltaic park will be built on the Tismana 2 – EMC Roșia - Rovinari spoil tip. The photovoltaic park is located within the Tismana Quarry, Tismana II spoil tip, longitude 23,12 E, latitude 44,93 N.

Main activities of the project

Activity Start date End date

1. Financing contract

2022

2023

2. Contracting procedures
Construction works

2023

2024

3. Execution of works

2025

2027

  • Design
  • Execution of works
  • Commissioning

2025
2025
2027

2026
2027
2027

4. Communication, information and publicity

2023

2027

Performance technical indicators of the investment

Item
No.
Indicator name Unit of measurement Target value Comments

1

Installed operational capacity for renewable energy generation

MWp

132

Minimum target value according to the provisions of Chapter 4.1, letter b) from Annex 4 – Submission form for investment proposals for priority investments*

2

Total CO2 savings

tCO2/an

147.933

According to the provisions of Chapter 4.1, letter c) from Annex 4 – Submission form for investment proposals for priority investments

3

Average electricity production from renewable sources

MWh/an

168.489

According to the provisions of Chapter 4.1, letter b) from Annex 4 – Submission form for investment proposals for priority investments*

*b) Minimum indicators, namely performance indicators – physical elements/physical capacities that indicate achievement of the investment objective target – and, where applicable, qualitative indicators, in accordance with the applicable standards, norms, and technical regulations.

Installed power
of Tismana 2 Solarist Photovoltaic park

~132 MW