Parc Fotovoltaic Tismana 1 - Parc Verde

Main activities of the TISMANA 1 PHOTOVOLTAIC PARK

The design and execution of a photovoltaic park with an installed power of 128,3 MW on the slag and ash deposits of the spoil tip in Tismana Quarry.

Project developed by
Supported by

TISMANA 1
PHOTOVOLTAIC PARK AT A GLANCE

Project name

Construction of a Photovoltaic Park on the inner dump within Tismana 1 – Roșia – Rovinari quarry mining unit -

The total value of the Project is 567,890,930 lei (equivalent in lei of 114,406,489 euro), of which the maximum insured value from the Modernization Fund is 397,523,650 lei (equivalent in lei of 80,084,542 euro -70% of the total value of the Project).

Location

The Tismana 1 photovoltaic park will be built on the Tismana 1 spoil tip of SE Rovinari of Tismana Quarry, operating perimeter Tismana II, between 192-220m elevation, longitude 23,09 E, latitude 44,94 N.

Main activities of the project

Activity Start date End date

1. Financing contract

2022

2023

2. Contracting procedures
Construction works

2023

2024

3. Execution of works

2024

2025

  • Design
  • Execution of works
  • Commissioning

2024
2024
2025

2024
2025
2025

4. Communication, information and publicity

2023

2025

Performance technical indicators of the investment

Item
No.
Indicator name Unit of measurement Target value

1

Installed operational capacity for renewable energy generation

MWp

128

2

Total CO2 savings

tCO2/an

130.450

3

Average electricity production from renewable sources

MWh/an

148.577

Installed power
of Tismana 1 Photovoltaic park

~128 MW